.ShanXi
Huaxin calcium carbonate project
Design
a steel structure platform with 3 separated equipments of totally 36 tons, analyze
the structure with frame analysis software, considering dead loads and
earthquake loads. Design several pump and tank foundations, storage and
reaction ponds. Carry out site service as design representative for 2
weeks. Propose site technical solutions for wire and pipe truss supports.
.Beijing
Organic Chemical Plant VAE project
Choose
the structural system and execute detailed design for a 60Mx24M concrete
framed bent workshop. The job consists of the production of calculation
reports and shop drawings. Four single beam cranes suspending under the
roof angle steel truss is the key problem of the project. The simple and
reliable welding joints are designed to assure the connection of crane
beams to the roof truss. The work also include a concrete viaduct for the
pipe and wire.
.Qingdao DIC Fine Chemicals Co. QDP-1 project
Execute detailed design for a two store concrete framework as the utility
house. PKPM program is used to analysis and design the whole structure and
concrete elements. Special construction process considering equipments
installation is reflected in the design.
.ShanDong
ShengDa carbonate calcium project
Design a
200m long heavily loaded steel pipe rack serving the whole plant, a masonry
and concrete combined utility house, a deep foundation sitting on the
rock for a large vessel which is 50m in height and 1500t in weight.
Supervise three university students who were internship in our company with
their Bachelor Degree thesis.
.YPC-BASF Integrated Petrochemical Plant project
Ethylene Unit. Working as structural designer for heavily loaded pipe rack
pile foundations, reactor foundations and compressor framework foundation.
2002-06---2003-03
Stone & Webster LTD ( A Shaw group
company) Civil Engineering Department
. YPC-BASF Integrated
Petrochemical Plant project (Nanjing)
Ethylene Unit. Working as the chief structural engineer on the site . Total
investment is 2.9 billion US,
more than 20000 cubic meter concrete was casted as equipment foundations
and 3000 precast piles were driven. Job including interpreting drawings,
make site solutions to imminent problems, quality inspection, cooperate
with HVAC engineers.
Site report of installation of
pre-cast piles.
|